| Tier | Signal | Date | Service Impact |
|---|---|---|---|
| Tier 3 |
Well pad is located on an aquifer, triggering mandatory NDIC Field Inspector site inspection and specific stipulations (closed mud system, impermeable liner).โฐ TIME-SENSITIVE ๐ Permit Information / Stipulations Aquifer location imposes non-standard, prescriptive environmental controls and requires regulator engagement before construction, adding cost and schedule complexity. |
2026-09-21 | Mud / Fluids |
| Tier 3 |
Operator requests waiver from Order 31973 notification requirements because they are the operator of the adjacent spacing unit the wellbore traverses. ๐ Letter to NDIC Permit Manager Demonstrates sophisticated regulatory strategy to streamline approval, avoiding delays from external notifications. |
2026-08-31 | Regulatory / Permitting |
| Tier 3 |
MWD Contractor explicitly pre-selected as 'KLX Directional'. ๐ Drilling Plan, Page 1 Vendor is named in the approved drilling plan, indicating a contracted service opportunity that is not open for bid. |
2026-08-20 | Directional Drilling |
| Tier 3 |
Pad layout shows four 'FUTURE SOUTH WELL' locations alongside existing wellheads, indicating a multi-well development plan. ๐ As-Built Pad Layout Reveals operator's intent for sequential development, creating a pipeline of drilling, completion, and production services at this pad. |
2026-07-23 | General Oilfield Services |