Tier Signal Date Service Impact
Tier 3 Operator is coordinating a multi-well pad (Maverick and Top Gun wells) and has filed for a waiver to the 'backbuild order' notification requirements.โฐ TIME-SENSITIVE
๐Ÿ“„ Letter from Meaghan Coughlan dated September 9th, 2026
The letter demonstrates proactive regulatory engagement for a multi-well development plan, indicating advanced stage planning and imminent activity.
2026-09-09 Regulatory / Permitting
Tier 3 Completion design specifies use of a 'wet shoe with ability to frac out the toe'.
๐Ÿ“„ Permit Stipulations / Conditions of Approval and Proposed Work / Stimulation section
This is a specific completion technique choice detailed in the permit, differing from a standard plug-and-perf design.
Unknown Completions / Frac
Tier 3 NDIC Field Inspector Marc Binns must be contacted prior to location construction.
๐Ÿ“„ Permit Stipulations / Conditions of Approval
The condition names a specific inspector and creates a mandatory pre-construction checkpoint not required for all permits.
Unknown General Oilfield Services
Tier 3 Operator has pre-selected Smoky Butte Environmental LLC for drill cuttings disposal.
๐Ÿ“„ Proposed Work / Disposal of Drill Cuttings section
Vendor is explicitly named in the permit's proposed work plan, indicating a locked-in service contract rather than an open bid.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Drilling Waste Management / Hauling
Permit locks in Smoky Butte Environmental LLC for cuttings disposal, eliminating near-term opportunity for competitors unless a change is filed.
Directional Drilling / Surveying
Complex multi-well pad with precise anti-collision requirements and a mandated survey program indicates need for advanced directional services.
Completion Services (Stimulation)
The specified wet shoe completion technique creates a need for specialized frac initiation services at the toe of the lateral.
Civil Construction / Earthwork
Detailed pad layout with ~98,550 cu yds of earthwork and specific compaction standards indicates a major site construction project is planned.