๐Ÿ›ข๏ธ Huron State 24-36 36-25 TF2H

True Oil LLC ยท McKenzie County, ND ยท File #43344 ยท Generated 2026-10-01 04:19

API
3305310894
Target Formation
Three Forks Upper
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 3 BLM notification required due to federal minerals in spacing unitโฐ TIME-SENSITIVE
๐Ÿ“„ Email from Nathaniel Erbele to Sergio Villa
Permitting engineer flags that the well is in a unit with federal minerals, requiring operator to contact BLM before drilling. This adds a regulatory step.
2026-09-25 General Oilfield Services
Tier 3 Explicit waiver of diesel fuel use in hydraulic fracturing submitted
๐Ÿ“„ Letter from Sergio Villa to Todd Holweger
Operator proactively submitted a formal statement confirming diesel fuel will not be used in frac operations, addressing a specific regulatory requirement ahead of time.
2026-07-28 Completions / Frac
Tier 3 Drill cuttings disposal pre-approved to specific facilities
๐Ÿ“„ Letter from Sergio Villa to Daniel Kuchar
Operator has pre-selected and declared specific waste disposal vendors (Ideal Oilfield Disposal or IHD Solid Management) before drilling, indicating a locked-in service contract.
2026-07-28 General Oilfield Services
Tier 3 Drill-back waiver request for wellbore exiting target spacing unit
๐Ÿ“„ Drill Back Waiver Request Letter
Well plan involves lateral exiting the target unit (Sec 25) and entering adjacent Sec 1. Operator has submitted a waiver acknowledging requirement to notify any future operator in that section.
Unknown Regulatory / Permitting
Tier 3 Mandatory pre-construction contact with specific NDIC field inspectorโฐ TIME-SENSITIVE
๐Ÿ“„ Permit Stipulations
Permit condition requires operator to contact NDIC Field Inspector Will Ryan prior to location construction, specifying the inspector's name and phone number.
Relative General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

H2S Safety Services & Equipment
A detailed H2S plan is in place with a named vendor (Total Safety Inc.), but equipment must be installed and operational 500' above or 3 days prior to penetrating the H2S zone, creating a time-sensitive mobilization window.
Waste Hauling/Disposal
Cuttings disposal is pre-contracted to two named facilities. Hauling services to these specific sites are required once drilling generates cuttings.
Cementing Services & Centralizers
The detailed cementing program specifies large volumes of specialized cement (VariCem, NeoCem, ExtendaCem) and over 300 centralizers, indicating a significant cementing job opportunity.
Directional Drilling/MWD Services
The complex well path with a build section and long lateral requires precise directional drilling and survey services, as outlined in the plan.