๐Ÿ›ข๏ธ Huron State 34-36 36-25 TF3H

TRUE OIL LLC ยท McKenzie County, ND ยท File #43345 ยท Generated 2026-09-30 06:59

API
3305310895
Target Formation
Three Forks
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 3 NDIC engineer flags that the well's spacing unit may be subject to a Federal permit and instructs operator to contact the BLM Dickinson office.โฐ TIME-SENSITIVE
๐Ÿ“„ Email from NDIC permitting engineer dated 25 September 2026.
Introduces a potential regulatory hurdle and inter-agency coordination requirement immediately after state permit approval.
2026-09-25 General Oilfield Services
Tier 3 Operator has declared pre-selected drill cuttings disposal facilities: Ideal Oilfield Disposal or IHD Solid Management.
๐Ÿ“„ Regulatory compliance letter dated 8 September 2026.
Explicitly names two specific waste disposal contractors in a regulatory filing, reducing competitive opportunity for others.
2026-09-08 General Oilfield Services
Tier 3 Permit condition: 'True Oil must contact NDIC Field Inspector Will Ryan at 701-770-6684 prior to location construction.'
๐Ÿ“„ Permit stipulations page.
Names a specific field inspector as a mandatory point of contact, creating a procedural gate before pad construction can begin.
Unknown General Oilfield Services
Tier 3 Operator plans to use a Halliburton RapidStart Initiator Sleeve on the production liner toe.
๐Ÿ“„ Drilling program details within the permit application.
Specifies a proprietary completion tool from a major service company, indicating pre-selection for the completion phase.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling / MWD Services
The detailed anticollision report and planned survey program indicate imminent drilling activity requiring precise wellbore placement amidst existing wells.
Cementing & Centralizer Services
The detailed cementing program specifies large volumes and centralizer counts (e.g., ~200 solid body centralizers for the production liner), indicating a major cementing job is planned post-drilling.
Pad Construction & Earthwork
The permit is approved and includes a detailed pad grading plan with cut/fill quantities. The construction notification requirement to Inspector Will Ryan is a immediate next step.