๐Ÿ›ข๏ธ GO-Beyer- 158-98-3415H-1

HESS BAKKEN INVESTMENTS II, LLC ยท Williams County, ND ยท File #43347 ยท Generated 2026-10-01 04:21

API
3310506897
Target Formation
Middle Bakken
Confidence
High

๐Ÿ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 Approval condition includes a 150' north setback based on a production liner cemented in the lateral with a wet shoe and the ability to frac out the shoe.
๐Ÿ“„ Permit stipulations
Specific completion design (cemented liner with wet shoe) is tied to a regulatory setback condition, indicating a non-standard wellbore construction plan to meet spacing rules.
Unknown Completions / Frac
Tier 3 Affidavit confirms a Surface Use Agreement is in place with landowners for off-spacing operations, dated effective March 1, 2026.
๐Ÿ“„ Drilling Permit Affidavit
Securing surface access for off-spacing wells is a critical pre-drilling milestone; the affidavit provides proof and a specific execution date.
2026-03-01 General Oilfield Services
Tier 3 Affidavit from Hess Senior Manager states Halliburton Energy Services is the stimulation treatment supplier and does not use diesel fuels in fracturing.
๐Ÿ“„ Hydraulic Fracturing Stimulation affidavit
Identifies Halliburton as the pre-selected frac vendor via a historical affidavit, establishing a long-standing vendor relationship for completions.
2022-04-21 Completions / Frac
Tier 3 Operator must contact NDIC Field Inspector Robert Stafford prior to location construction.
๐Ÿ“„ Conditions of Approval
Pre-construction contact with a specific inspector is a mandated step, creating a defined regulatory checkpoint before pad work begins.
Relative General Oilfield Services
Tier 3 Integrated well pad design for six wells includes detailed civil engineering, stormwater management, and interim reclamation plans.
๐Ÿ“„ Civil layout and plan notes
The document contains extensive, engineered pad construction details far beyond a typical permit, indicating a major, planned multi-well pad development.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Civil Construction & Earthwork
Detailed engineered pad plans exist, and construction cannot commence until the operator contacts the NDIC inspector, indicating imminent pad-building activity.
Directional Drilling & MWD/LWD
A detailed directional plan from Scientific Drilling is in place, and anti-collision protocols require precise surveying and geosteering, indicating need for directional services.
Cementing Services
The approved well design mandates a cemented production liner with a wet shoe to facilitate 'frac out,' indicating a specific cementing job design is required.
Hydraulic Fracturing
Although Halliburton is pre-selected per a 2022 affidavit, the well is designed for a multi-stage completion, confirming a near-term frac campaign is planned post-drilling.