๐Ÿ›ข๏ธ Ross 59-0515H

EOG RESOURCES, INC. ยท Mountrail County, ND ยท File #43413 ยท Generated 2026-10-16 06:59

API
3306105726
Target Formation
BAKKEN
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 2 Approval conditioned on ability to 'frac out the shoe' of a cemented production liner with a wet shoe.
๐Ÿ“„ Permit Stipulations
The stipulation explicitly ties regulatory approval to a specific liner cementing and completion method, deviating from a standard cemented liner.
2026-10-15 Completions / Frac
Tier 3 Operator must contact NDIC Field Inspector Dylan Roach prior to location construction.โฐ TIME-SENSITIVE
๐Ÿ“„ Permit Conditions
The condition mandates direct contact with a named inspector, creating a specific procedural step before pad construction can begin.
2026-10-15 General Oilfield Services
Tier 3 Pad construction involves 39,500 C.Y. of excavation and 65,335 C.Y. of embankment for the ROSS 5 NENW/CTB/NWNW complex.โฐ TIME-SENSITIVE
๐Ÿ“„ Engineering Plat Notes
The volume of cut/fill is explicitly quantified in the civil engineering plans, indicating a major site preparation effort is either planned or underway.
2026-07-07 General Oilfield Services
Tier 3 Drilling plan notes '102 Proposed Stages' for the lateral.
๐Ÿ“„ Casing & Cementing Program Notes
The stage count is explicitly proposed in the engineering design, indicating a high-intensity completion design.
Unknown Completions / Frac

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Civil Construction & Earthwork
Detailed pad construction plans with massive cut/fill volumes (e.g., 39,500 C.Y. excavation) are finalized and approved, indicating imminent or ongoing site preparation.
Cementing & Downhole Tools
The approved plan requires a specific 'wet shoe' liner cementing job and subsequent 'frac out' operation, creating a non-standard service need tied to the permit's stipulations.
Hydraulic Fracturing & Pumpdown
A 102-stage frac design is proposed, and the operator has affirmed no diesel use in frac fluids via a recent affidavit (Sept 2026), indicating completion planning is advanced.
Surveying & Directional Drilling
A detailed directional plan with anti-collision analysis is included, and a specific surveying vendor (Superior MWD+IFR1+SAG+FI) is named in the plan, suggesting vendor selection may be underway.