โ† Back to Daily Permits

๐Ÿ›ข๏ธ LAR1-23-02 S516H

FORMENTERA OPERATIONS, LLC ยท Burke County, ND ยท File #43446 ยท Generated 2026-11-03 02:52

API
3301302092
Target Formation
Bakken
Confidence
High

๐Ÿ“Š Signals (4)

Tier Signal Date Service Impact
Tier 3 Off-spacing development requiring a signed Surface Use Agreement affidavit due to surface location outside the 1920-acre spacing unit.
๐Ÿ“„ Off-Spacing Affidavit section
Indicates operator is willing to secure surface agreements and manage regulatory complexity to access the unit from an optimal pad location, revealing strategic land planning.
2026-10-22 General Oilfield Services
Tier 3 Wellbore anticollision analysis shows close approach (4.45 ft) to an offset well at shallow depth, requiring collision risk procedures.โฐ TIME-SENSITIVE
๐Ÿ“„ Anticollision Report summary
Highlights non-routine drilling hazard requiring precise directional control and monitoring from the very start of the well.
2026-10-21 Directional Drilling
Tier 3 Operator plans to request waivers for both the on-site filter sock container and open-hole logging requirements, citing no filtration use and reliance on offset well data.
๐Ÿ“„ Preliminary Drilling Program section
Shows operator intent to streamline operations by avoiding routine containment and logging, which requires regulatory filing and approval.
Relative Regulatory / Permitting
Tier 3 Detailed spill response plan with SCADA, automatic shutoffs, thermal cameras, and fiber optic leak detection specified for production.
๐Ÿ“„ Spill Prevention and Spill Response Plan section
Exceeds basic regulatory requirements, indicating a high investment in automation and environmental risk mitigation.
Unknown General Oilfield Services

๐Ÿ’ก Operator Intent

๐Ÿ”ง Service Operator Relevance

Directional Drilling & Surveying
Anticollision report flags a very close approach (4.45 ft) at shallow depth, demanding high-precision directional control from spud; directional plan dated 10/21/2026.
Regulatory & Sundry Filing
Operator states intent to file sundry notices for waivers (filter container, open-hole logs) upon permit approval, creating immediate filing work.
Advanced Monitoring & Automation
Detailed plans for SCADA, automatic shutoffs, thermal cameras, and fiber optic leak detection indicate procurement and integration needs for the production phase.
Waste Hauling & Disposal
Closed-loop drilling system with named disposal facility (Prairie Disposal) indicates ongoing need for cuttings hauling during drilling.