πŸ›’οΈ ALE 1534-3BHN

KODA RESOURCES OPERATING, LLC Β· Divide County, ND Β· File #43453 Β· Generated 2026-11-06 03:29

API
3302301922
Target Formation
Middle Bakken
Confidence
High

πŸ“Š Signals (5)

Tier Signal Date Service Impact
Tier 2 North setback condition based on production liner cemented in lateral with wet shoe and ability to frac out the shoe.
πŸ“„ NDIC Field Order Info
Specifies a precise completion design (cemented liner with wet shoe) as a condition of approval for boundary setbacks, locking in a specific completion method.
Unknown Completions / Frac
Tier 3 Closed loop system mandated; all drill cuttings to be disposed at 13 Mile Landfill, Williston, ND.
πŸ“„ Drilling Plan - Drilling Fluids Program
Pre-selects a specific offsite disposal facility and mandates a closed-loop drilling system, dictating waste handling logistics.
Unknown Mud / Fluids
Tier 3 Well pad located on an aquifer triggers mandatory onsite inspection and closed mud system with impermeable liner.
πŸ“„ PERMIT INFORMATION / STIPULATIONS
Imposes strict environmental controls and requires NDIC Field Inspector involvement before construction, adding regulatory steps and potential for site-specific stipulations.
Unknown Mud / Fluids
Tier 3 Operator must wait 3rd business day after permit publication before commencing operations unless Director waives.⏰ TIME-SENSITIVE
πŸ“„ Conditions of Approval
Introduces a mandatory waiting period that can delay spud, affecting rig scheduling and pad timing unless a waiver is actively sought.
Relative Drilling Rigs
Tier 3 Operator plans to submit a sundry to waive open hole logs, relying on MWD and cased-hole evaluation.
πŸ“„ Drilling Plan - Evaluation Program
Non-routine data acquisition strategy reduces open-hole logging, shifting focus to MWD and cased-hole logs, which may affect service mix.
Unknown General Oilfield Services

πŸ’‘ Operator Intent

πŸ”§ Service Operator Relevance

Environmental & Site Compliance
Aquifer location triggers immediate need for onsite inspection, closed mud system, impermeable liner, and perimeter bermβ€”all required before construction commences.
Waste Hauling & Disposal
Closed-loop system mandated with cuttings destined specifically for '13 Mile Landfill, Williston, ND', creating a fixed disposal contract.
Directional Drilling & MWD
KLX Directional is pre-selected as MWD contractor; anti-collision planning is complete and required for pad drilling with multiple wellbores.
Cementing & Pressure Control
Cemented liner with wet shoe design is a permit condition, requiring specialized cementing services and pressure testing for frac-out.