โ† Back to Daily Permits

๐Ÿ›ข๏ธ CCU North Coast 31-25MBH

Burlington Resources Oil & Gas Company LP ยท Dunn County, ND ยท File #26387 ยท Generated 2026-04-04 15:56

API
Unknown
Target Formation
Middle Bakken Dolomite
Permit Explained
Yes

๐Ÿ“‹ Permit Cycle Assessment

The permit approval dated September 6, 2013 (File No. 26387) is directly conditioned by: (1) Commission Order No. 18849 setback requirements (200 ft N/S, 500 ft E/W) within the Corral Creek-Bakken Unit; (2) mandatory perimeter dike construction with pre-construction inspection by NDIC Field Inspector Ashleigh Devenberg; (3) three-day waiting period for location construction commencement after permit publication; (4) survey frequency and directional plan requirements (100 ft intervals vertical, 30 ft in curve, 90 ft in lateral); (5) approved open hole log waiver (August 19, 2013) requiring GR to surface, CBL on production casing, and mud log submission. Subsequent regulatory stipulations (filter sock container requirement effective June 1, 2014; cores and samples submission within 30/90 days per NDCC 38-08-04) became binding post-approval but pre-spud. The well spud October 9, 2014, approximately one year after permit approval, under these conditions. No evidence of permit modification or additional approvals between September 6, 2013 and spud date.

๐Ÿ” Permit Cycle Signals (5)

Permit approval issued by NDIC with specific setback requirements and perimeter dike stipulation
Direct
๐Ÿ“„ September 6, 2013 NDIC Approval Letter
๐Ÿ“… 2013-09-06 (Exact confidence)
Approval conditioned on 200-foot setback (N/S) and 500-foot setback (E/W) within CORRAL CREEK-BAKKEN UNIT, per Commission Order No. 18849. Perimeter dike required; field inspector contact mandatory before location construction.
Three-day waiting period for location construction commencement after permit publication on NDIC Daily Activity Report
Direct
๐Ÿ“„ September 6, 2013 NDIC Approval Letter
๐Ÿ“… 2013-09-06 (Exact confidence)
Standard operational constraint tied to permit approval; operators must wait 3 business days following publication unless Director waiver obtained by sworn affidavit.
Permit stipulation requiring covered leak-proof container for filter sock disposal effective June 1, 2014
Supporting
๐Ÿ“„ April 16, 2014 NDIC Permit Stipulation Letter (File No. 26387 listed)
๐Ÿ“… 2014-06-01 (Exact confidence)
Regulatory condition binding on all permits not yet spud as of April 16, 2014. Container must be maintained from spud through completion/flow-back if filtration operations conducted. This well was spud October 9, 2014, after the effective date.
Cores and samples collection requirement per NDCC Section 38-08-04
Supporting
๐Ÿ“„ September 9, 2013 NDIC Letter to Donna Williams
๐Ÿ“… 2013-09-09 (Exact confidence)
All cuttings from Base of Last Charles Salt forward at 30-foot maximum intervals (vertical, build, and lateral sections) must be submitted within 30 days of drilling completion. Cores must be preserved and shipped within 90 days. Civil penalty up to $12,500 per violation per day.
Open hole log waiver approved with alternative GR and CBL requirements
Direct
๐Ÿ“„ August 19, 2013 NDIC Waiver Approval (File No. 26387)
๐Ÿ“… 2013-08-19 (Exact confidence)
Operator requested and NDIC approved waiver from full suite open hole logs based on correlation to offset well BN 1-23 (File #7576). Approval conditioned on: (1) GR log from KOP to ground level; (2) CBL on production casing; (3) mud log; (4) submission of two digital copies each in TIFF and LAS format.

๐Ÿ“– Historical Context (5)

Pad surface instability and relocation during construction (August 4, 2014)
๐Ÿ“„ August 4, 2014 Sundry Notice (Form 4) - Surface Move request ยท ๐Ÿ“… 2014-08-04
Operator reports soil instability caused pad slide during construction; requests approval to relocate surface location from 469 FNL & 804 FEL to 526 FNL & 353 FEL within same quarter-section (NENE Sec. 25-147N-95W). Impacted area reclamation completed. New location required revised drill plan package submission. This relocation modifies the original permit geometry and required NDIC approval before proceeding with drilling operations.
Permit renewal submitted August 28, 2014; Permits expire annually in North Dakota
๐Ÿ“„ August 28, 2014 Permit Renewal Notice (SFN 5748) ยท ๐Ÿ“… 2014-08-28
Initial permit issued September 6, 2013 with one-year validity expiring September 6, 2014. Operator submitted renewal Form 4 on August 28, 2014 requesting permit extension and charging fee to credit card on file. Renewal was required to maintain drilling authorization and was approved prior to spud (October 9, 2014). Failure to renew would have invalidated the permit.
Gas Capture Plan submission for CCU North Coast Quad Pad (August 13, 2014)
๐Ÿ“„ August 13, 2014 Gas Capture Plan Affidavit and Capacity Analysis ยท ๐Ÿ“… 2014-08-13
Burlington submitted detailed gas capture plan for CCU North Coast 31/41-25 Quad Pad (four wells including this well) coordinating with ONEOK processing infrastructure. Anticipated first production April 2015. Flowback strategy: sequential high-rate flowbacks 2-4 days per well at 1,000โ€“4,000 Mcfd. Statewide flaring 26%; CCU fieldwide 14% (June 2014). Plan details monthly production rates (Month 1: 650โ€“1,000 bopd per well; Month 12: 150โ€“250 bopd) and compressor capacity (Lost Bridge 35,000 Mcfd; Lone Butte 12,000 Mcfd; future North Dunn station 30,000 Mcfd). Governs post-drilling completion and sales operations.
Quarterly Development Plan updates (Q1, Q2, Q3 2013) showing well pad consolidation and location adjustments
๐Ÿ“„ Q1 (January 21, 2013), Q2 (March 28, 2013), Q3 (July 3, 2013) Quarterly Updates to NDIC ยท ๐Ÿ“… 2013-01-21
Operator committed to providing quarterly updates on modifications to the Corral Creek-Bakken Unit Development Plan per NDIC conference call directive (January 7, 2013). Pad S (four-well quad pad, including this well) was identified in Q1-2013 as new location in NE/4 Section 25, T147N-R95W scheduled for 2013 drilling. Updates document landowner accommodation efforts, surface disturbance minimization, and coordination with Little Missouri State Park (easement for riding trail in Section 25; seasonal operations window). Historical context: pad was initially planned but location and schedule evolved through 2013 based on construction feasibility and regulatory feedback.
Corral Creek-Bakken Unit (CCU) unitization and development framework
๐Ÿ“„ References throughout to NDIC Case Nos. 15332 and 15333; Commission Order No. 18849 ยท ๐Ÿ“… 2011-10-12
CCU is a designated spacing unit with approved Development Plan ('Preliminary Lost Bridge Unit 3 Rig Development Plan') submitted October 12, 2011. All individual well drilling permits (including File No. 26387) are conditioned by unit-level decisions regarding drilling density, spacing, setbacks, and unitized development schedule. Setback requirements and operational constraints flow from unit geometry and order, not solely from individual well permits.

๐Ÿ”ง Operator Pattern

Burlington Resources Oil & Gas (ConocoPhillips subsidiary) demonstrates systematic approach to regulatory compliance and stakeholder engagement within Corral Creek-Bakken Unit: committed to quarterly reporting of development plan modifications; proactively addressed landowner concerns through pad relocations and consolidation; coordinated with state park authorities on operational timing to minimize environmental and recreational impacts; adapted to field conditions (e.g., soil instability requiring mid-construction surface relocation); submitted supplemental technical documentation (gas capture plans, geological correlation studies) to support operational decisions.
Quarterly updates (Q1โ€“Q3 2013) document multiple pad relocations to accommodate landowner preferences and minimize surface disturbance (Pad A moved from SW/4 Sec. 19 to NW/4 Sec. 30; Pad H moved from NE/4 Sec. 28 to SE/4 Sec. 21; Pad U and V relocated from Sections 31 and 5 to Sections 18 to mitigate environmental risk re: Little Missouri River drainage). Gas Capture Plan (August 2014) shows coordination with ONEOK and transparent disclosure of anticipated production rates and flaring percentages. Surface move request (August 2014) demonstrates rapid response to construction-phase challenges with documented reclamation. Permit renewal and waiver submissions show timely compliance with renewal deadlines and regulatory documentation requirements.
Confidence: High
Well file contains complete permit approval (September 6, 2013) with explicit conditioning language, regulatory stipulations (filter sock container, cores/samples, log waivers) tied by date and file number, and contemporaneous operational documents (pad move, permit renewal, gas capture plan, survey data). Dates are consistently sourced from official NDIC and operator correspondence. No material ambiguities in permit-cycle timeline or conditioning authority. Historical context is clearly distinguished (unit development plan, prior pad planning, operator profile) and does not conflate with permit-specific justifications. Directional survey data (Weatherford 5D 7.5.9, January 30, 2015) provides post-drill verification of well geometry against planned directional design. Only material gap: specific explanation for ~one-year delay between permit approval (September 6, 2013) and spud (October 9, 2014) is not explicitly stated in file, though surface construction complications (soil instability, pad relocation August 4, 2014) and permit renewal requirements (August 28, 2014) provide contextual rationale.