OTHER
Wellfile updated - +17 pages
Jefferson Federal 5003 42-14 9B
WHITING OIL AND GAS CORPORATION · McKenzie County, ND · File #41439 · Generated 2026-11-27 02:13
- API
- 3305310465
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The permit cycle is explained by a direct regulatory approval for a suspension of drilling operation, which allows a staged, two-rig approach with specific monitoring and reporting requirements. A prior permit renewal also preserved the original approval conditions.
Permit Cycle Signals (3)
Sundry Form ID: 324238
2026-07-07 (Exact confidence)
Direct regulatory request and approval for a staged drilling operation that alters the standard drilling sequence and requires specific monitoring.
Sundry Form ID: 324238 Reviewer Comments
2026-07-14 (Exact confidence)
Direct conditions of approval for the suspension of drilling permit, imposing specific reporting and operational constraints.
Sundry Form ID: 291289
2026-01-06 (Exact confidence)
Direct action extending the validity of the original permit and its conditions, a prerequisite for subsequent operations.
Historical Context (4)
Cores and cuttings must be submitted to State Geologist per NDCC 38-08-04 and NDAC 43-02-03-38.1, with specific collection intervals.
Letter from Ross Edison, Geologist · 2024-12-30
A persistent geoscientific obligation that must be fulfilled upon completion of drilling, regardless of the permit cycle.
Open hole log waiver approved based on offset well data, requiring only a GR-CBL from TD to ground level.
Sundry Form ID: 248454 · 2025-05-20
A permanent modification to the standard logging program that dictates the well evaluation deliverables.
Setback condition (150' N/S, 500' E/W) within the 1920-acre spacing unit per Commission Order No. 32449, with specific south setback justification based on cemented production liner and wet shoe.
Permit Stipulations · 2024-12-18
A foundational geometric and regulatory constraint for well placement and completion design that persists for the life of the well.
Requirement for a leakproof, covered, placarded filter sock container on site from spud through flow-back, per NDAC 43-02-03-19.2.
Letter from Assistant Director · 2023-08-28
A permanent waste management obligation attached to the well site during active operations.
Operator Pattern
Multi-well pad development with coordinated anti-collision planning and standardized 'wet shoe' completion design.
Anticollision report shows planned proximity to other wells on the Jefferson Federal pad (e.g., 2.1' from 10BX). Drilling workbook details standard wet shoe configuration for toe initiation. Pad layout shows 10 wells on a single graded pad.
Confidence: High
Key permit-cycle documents (suspension request, renewal) have explicit dates, regulatory reviewer comments, and approval statuses. Historical signals are from clear regulatory orders and letters with enduring requirements.