NO COMPARISON
Well file changed - no earlier copy to compare
First detected 2026-10-26 · Full diff →

GO-ZONA-157-98-3523H-2

Hess Bakken Investments II, LLC · Williams County, ND · File #41778 · Generated 2026-11-27 02:13

API
3310506501
Target Formation
Middle Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit approval is explained by contemporaneous regulatory actions, including an open hole log waiver, a suspension of drilling approval, specific setback conditions tied to completion design, and a pre-construction notification requirement. Supporting submissions justify cross-unit drilling and anti-collision planning.

Permit Cycle Signals (5)

Open hole log waiver granted based on offset well GO-JOHN-156-98-0508H-3 within a mile having sufficient logs to establish formation tops.
Direct
Sundry Form ID 240758 (Open Hole Log Waiver)
2025-04-08 (Exact confidence)
Waiver eliminates routine logging requirement, conditioning permit approval on alternative data source.
Suspension of Drilling (SOD) approved for up to 90 days to allow drilling surface hole with a smaller rig before moving on a larger rig to TD.
Direct
Sundry Form ID 240753 (Suspension of Drilling)
2025-04-08 (Exact confidence)
Regulatory approval for a non-standard drilling sequence, conditioning the permit on a specific operational timeline and procedure.
Permit stipulation requiring 150' setback from N/S boundaries and 500' from E/W boundaries within the 1920-acre spacing unit, with north setback justified by a cemented production liner with a wet shoe.
Direct
Permit Stipulations (NDIC Field Order Info, Bakken Setback Summary Statement)
2025-04-07 (Exact confidence)
Specific geometry constraint tied to a non-routine completion design (cemented liner with wet shoe) differentiates from standard setbacks.
Requirement to contact NDIC Field Inspector Robert Stafford prior to location construction.
Direct
Permit Stipulations (Construction Commencement Notification)
2025-04-07 (Exact confidence)
Direct regulator-imposed pre-construction condition.
Affidavit requesting waiver of Order 31848 requirements for adjacent unit notification, as Hess is the operator of the adjacent unit.
Supporting
Letter from John DeWitt Jr. dated 2025-02-04
2025-02-04 (Exact confidence)
Justifies permit approval for wells with planned drill-backs outside the target spacing unit by addressing cross-unit regulatory requirements.

Historical Context (2)

Cement stabilization of the pad completed on 2025-06-25, with a reclamation plan requiring future milling, sampling, and potential soil amendment to match pre-stabilization conditions.
Sundry Form ID 280393 (Notification of Work Performed - Location Stabilization) · 2025-06-25
Creates a forward obligation for final pad reclamation, requiring specific testing and remediation steps that affect site closure.
Affidavit confirming hydraulic fracturing treatments will not use specified diesel fuels, covering all Hess wells in the Bakken project.
Letter from Tom Richardson dated 2022-04-21 · 2022-04-21
Establishes a binding operational constraint on completion fluid chemistry for all subsequent wells, including this one.

Operator Pattern

Systematic use of regulatory waivers (log, SOD) and pad stabilization to optimize operations.
Multiple Sundry Forms (240758, 240753, 280393) show repeated requests for operational flexibility within regulatory frameworks.
Confidence: High
Clear, dated regulatory correspondence (Sundry approvals, letters) and permit stipulations directly tied to the permit approval date of 2025-04-07. Key signals have exact dates and explicit regulatory roles.