OTHER
Wellfile updated - +1 pages
LOOMER 11-2 6H
DEVON ENERGY WILLISTON, L.L.C · McKenzie County, ND · File #42172 · Generated 2026-11-27 02:13
- API
- 3305310645
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The permit approval is directly conditioned by Commission Order 34449 and a suite of non-routine stipulations related to the well's geometry (wet shoe justification for north setback), location within an Extra-Territorial Jurisdiction and on an aquifer, and specific technical requirements for deep surface casing and cement verification.
Permit Cycle Signals (4)
Permit Information - Stipulations, Page 2 of 11
2026-01-14 (Exact confidence)
Permit approval is explicitly tied to a specific Commission Order and a non-routine geometry justification (wet shoe completion).
Permit Information - Stipulations, Page 2 of 11
2026-01-14 (Exact confidence)
These are non-standard, site-specific conditions triggered by jurisdictional and aquifer siting, directly tied to permit approval.
Permit Information - Stipulations, Page 3 of 11
2026-01-14 (Exact confidence)
Specific technical stipulation conditioning approval based on wellbore construction and formation protection, differentiating it from routine surface casing.
Permit Information - Stipulations, Page 3-4 of 11
2026-01-14 (Exact confidence)
Extended CBL requirements beyond standard, tied to deep surface casing and verification of isolation, condition the permit.
Historical Context (3)
Operator's request for flexibility to add a Dakota intermediate casing string due to increased SWD activity and elevated Dakota pressures experienced on the adjacent SKAAR pad.
Proposed Work statement, Page 8 of 11 · Relative
Establishes a forward-looking operational contingency for potential high-pressure zones that could affect drilling execution and well design on this pad.
Site-specific stipulations from prior permit (e.g., aquifer location, ETJ, closed mud system, impermeable liner) remain binding for wellsite construction and operations.
Historical Permit (dated 2025-08-01) and current permit, Stipulations sections · Relative
These are structural, site-specific obligations (aquifer protection, jurisdictional rules) that persist through all phases of activity on this pad location.
Approved waivers for tubing/packer requirement, filter sock container for drilling, and open hole logs from prior regulatory actions.
Sundry Forms (Waivers) dated 2025-08-07 to 2025-08-11 · 2025-08-07
These approved variances modify standard regulatory requirements for this well's construction and logging program, affecting future operational compliance.
Confidence: High
The well file contains the approved permit document with explicit stipulations and references to Commission Orders. Dates are clearly presented. The distinction between current permit-cycle conditions and persistent historical obligations is clear.