Wellfile updated - +1 pages
First detected 2026-10-28 · was Aug 31, 2026 · +1 page · Full diff →

LOOMER 11-2 7H

DEVON ENERGY WILLISTON, L.L.C · McKenzie County, ND · File #42173 · Generated 2026-11-27 02:13

API
3305310646
Target Formation
BAKKEN
Permit Explained
Yes

Permit Cycle Assessment

The permit modification is directly explained by the verbal approval for MWD-failure contingency drilling, the new Commission Order (34449) with its specific geometric setbacks, and the associated waiver for north setback based on liner/wet shoe design.

Permit Cycle Signals (5)

Verbal approval to drill blind additional 347' from survey at 21348' due to MWD failure, with explicit risk warning.
Direct
INSPECTOR COMMENTS (Verbal Approval Type: MWD Failure)
Unknown (Missing confidence)
Direct regulatory authorization for non-routine drilling continuation after survey tool failure.
Approval of Permit Modification referencing Commission Order No. 34449 and specifying lateral geometry-based setbacks (150' N/S, 500' E/W) for the 1280-acre unit.
Direct
PERMIT INFORMATION (Type: Permit Modification) - Stipulations
2026-01-14 (Exact confidence)
Direct condition of approval anchoring the permit to a new spacing/geometric configuration.
Stipulation tying north setback waiver to use of a production liner with a wet shoe and ability to frac out the shoe.
Direct
PERMIT INFORMATION (Type: Permit Modification) - Conditions of Approval
2026-01-14 (Exact confidence)
Direct modification of standard setback tied to specific well construction (liner with wet shoe).
Waiver request (approved 2025-08-11) for tubing/packer requirement (NDAC 43-02-03-21) based on casing specs, safety factors, and monitoring assurances.
Supporting
WELL SUNDRY FORM (Sundry Type: Request for Consideration/Waiver - Tubing/Packer Waiver)
2025-08-11 (Exact confidence)
Supporting technical submission justifying a non-standard completion design, preconditioning permit operations.
Sundry notice for Spud Date (05/07/2026) submitted, confirming drilling commencement.
Supporting
WELL SUNDRY FORM (Sundry Type: Notification of Work Performed - Spud Date)
2026-05-07 (Exact confidence)
Records execution of the permitted activity, closing the permit cycle.

Historical Context (4)

Location within Watford City's Extra-Territorial Jurisdiction and on an aquifer triggers extensive site-specific stipulations (closed mud system, liner, casing in rat/mouse hole, etc.).
PERMIT INFORMATION (Permit Modification) - Stipulations · 2026-01-14
Imposes persistent, non-routine construction and environmental protection obligations for all operations on this pad.
Requirement for deep surface casing (13-3/8") with prohibitions against penetrating the Mowry Formation and mandatory mud logging from surface to TD of surface hole.
PERMIT INFORMATION (Permit Modification) - Stipulations · 2026-01-14
Imposes a specific, persistent casing design and drilling surveillance obligation due to subsurface conditions.
Cement Bond Log (CBL) requirements on multiple casing strings (13-3/8" surface, 9-5/8" intermediate, 7" production) with zero-pressure pass.
PERMIT INFORMATION (Permit Modification) - Stipulations · 2026-01-14
Persistent, enhanced cement verification mandate affecting well construction timeline and procedures.
Operator's stated intent for flexibility to add a Dakota string if needed, referencing elevated Dakota pressure on nearby SKAAR pad.
PROPOSED WORK section in permit documents · 2026-01-14
Documents a known subsurface pressure hazard that may require future well design modifications.

Operator Pattern

Proactive engagement on complex pad siting (aquifer, ETJ), extensive use of waivers (tubing/packer, filter sock, open hole logs), and submission of BMP letters.
BMP letter (July 2025), pad siting analysis exhibit, multiple approved waiver sundries (Aug 2025), and direct communication with city planner.
Confidence: High
Key permit-cycle documents (verbal approval, permit modification with Order 34449) are present and clearly date-anchored. Historical stipulations are explicitly repeated in the permit. Text extraction, while imperfect, provides clear regulatory signals.