Well file changed - no earlier copy to compare
First detected 2026-10-28 · Full diff →

LOOMER 11-2 8H

DEVON ENERGY WILLISTON, L.L.C · McKenzie County, ND · File #42174 · Generated 2026-11-27 02:13

API
3305310647
Target Formation
Middle Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit approval on 2026-01-14 is directly conditioned by Order 34449 and specific stipulations related to setbacks, location within Watford City's ETJ and on an aquifer, and deep surface casing requirements.

Permit Cycle Signals (3)

Permit conditioned by Commission Order No. 34449, which grants approval based on specific 150'/500' setbacks within the 1280-acre unit and a north setback due to a production liner cemented in the lateral with a wet shoe.
Direct
Permit Modification Stipulations, Page 2 of 12, Date: 1/14/2026
2026-01-14 (Exact confidence)
Direct regulatory order that conditions the permit approval; includes a non-routine setback justification (north setback based on production liner/wet shoe).
Requirement to contact NDIC Field Inspector Marc Binns prior to location construction due to well being within Watford City's Extra-Territorial Jurisdiction and on an aquifer, triggering additional site-specific stipulations.
Direct
Permit Modification Stipulations, Page 2 of 12, Date: 1/14/2026
2026-01-14 (Exact confidence)
Direct stipulation conditioning permit approval based on location within ETJ and on an aquifer, requiring pre-construction contact and inspection.
Deep surface casing stipulation: 17-1/2-inch surface hole and/or 13-3/8-inch casing must not penetrate the Mowry Formation. Mud logger required from ground level to TD of surface hole. No intentional deviation in surface hole.
Direct
Permit Modification Stipulations, Page 3 of 12, Date: 1/14/2026
2026-01-14 (Exact confidence)
Direct technical stipulation differentiating this permit from routine horizontal wells; imposes specific drilling constraints and monitoring for deep surface casing.

Historical Context (3)

Well pad is located within Watford City's Extra-Territorial Jurisdiction and on the Tobacco Garden aquifer, requiring an onsite inspection and site-specific stipulations (closed mud system, no drilling pit, impermeable liner, H2S plan, fencing, berm, etc.).
Permit Modification Stipulations, Page 2 of 12, Date: 1/14/2026 · 2026-01-14
Persisting operational and compliance obligations for the entire lifecycle of the well pad, affecting construction, drilling, and production phases.
Deep surface casing requirement (casing not to penetrate Mowry Formation) and associated mandates (mud logger, no deviation) due to aquifer protection and subsurface geology.
Permit Modification Stipulations, Page 3 of 12, Date: 1/14/2026 · 2026-01-14
Imposes permanent well design and drilling execution constraints for aquifer protection, affecting future drilling operations on this pad.
Operator's commitment to implement BMPs for aquifer protection, stormwater management, spill response, and site security as detailed in the July 22, 2025 letter, following geotech/groundwater analysis.
Operator Letter dated July 22, 2025 (Wehrung West BMP Letter) · 2025-07-22
Operator-assumed obligations for the pad's entire operational life, affecting environmental management, emergency response, and regulatory compliance.

Operator Pattern

Proactive regulatory engagement and commitment to site-specific best management practices for sensitive locations (aquifer, ETJ).
Submission of detailed BMP letter (July 22, 2025), coordination with Watford City planner, and provision of geotech/groundwater analysis for pad siting.
Confidence: High
Clear permit stipulations directly reference Order 34449 and condition approval. Historical signals are explicitly tied to persistent location constraints (aquifer, ETJ). Dates are document-derived.