TECHNICAL
Technical reports added - +9 pages
First detected 2026-10-22 · was Aug 19, 2026 · +9 pages · Full diff →

WEST SHELL 1-9-4H

IRON OIL OPERATING, LLC · Mountrail County, ND · File #42253 · Generated 2026-11-27 02:13

API
3306105570
Target Formation
Middle Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit approval (suspension of drilling effective 2026-08-14) is directly explained by the operator's request for staged drilling using two rigs and the regulator's conditional approval with specific notification requirements.

Permit Cycle Signals (3)

Regulatory approval for suspension of drilling for up to 90 days under NDAC 43-02-03-55, allowing use of a smaller rig to drill surface hole before bringing larger rig to total depth.
Direct
Sundry Form (Request for Consideration/Waiver) - Type of Work: Suspension of Drilling
2026-08-14 (Exact confidence)
Permit action is a temporary suspension waiver allowing staged drilling with two rigs, conditioning approval on specific timelines and procedures.
Regulator stipulation requiring immediate notification after spudding, plug bump information, and notification when conventional rig returns, plus monthly conventional rig updates.
Direct
Sundry Form Reviewer Comments section
2026-08-14 (Exact confidence)
Direct conditions attached to the suspension approval, creating specific reporting obligations tied to the staged drilling plan.
Operator's commitment to plug and abandon and reclaim well site if well not drilled by larger rotary rig within 90 days after spudding with smaller rig.
Supporting
Sundry Form DESCRIPTION (OPERATOR) section
2026-08-10 (Exact confidence)
Operator-submitted justification and contingency plan that supports the regulatory waiver request for staged drilling.

Historical Context (3)

Core and sample collection requirement from Base of Last Charles Salt onward, with specific sampling intervals and submission deadlines.
Cores and Samples letter from State Geologist · 2025-09-02
Mandatory geological sample collection and submission obligation persists through drilling completion and affects post-drilling reporting timeline.
Wet Shoe Sub completion design with inability to frac out the shoe, requiring bridge plug at toe.
Well Construction Diagram and associated notes · Unknown
Completion design constraint affects fracture stimulation operations and requires specific plugging procedures.
Permit setback conditions based on cemented lateral with wet shoe and no ability to frac out the shoe.
Permit Stipulations section - Bakken Setback Summary Statement · 2025-08-26
Well-specific geometry (cemented lateral with wet shoe) establishes permanent boundary setbacks that constrain completion operations.

Operator Pattern

Utilizes staged drilling approach with smaller rig for surface hole to achieve cost and time savings.
Explicitly stated in suspension request: 'to take advantage of the cost savings and time savings of using an initial rig that is smaller than the rig necessary to drill a well to total depth.'
Confidence: High
Contemporaneous sundry notice directly requests and explains the permit action with specific dates, regulatory citations, and operator commitments. Regulator comments provide clear conditions of approval.