LOOMER 11-2 XE 1H
DEVON ENERGY WILLISTON, L.L.C · McKenzie County, ND · File #42421 · Generated 2026-11-27 02:13
- API
- 3305310720
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The permit modification is directly explained by contemporaneous documentation. The primary justification is a change to the directional plan, moving the initial kick-off point to 2300' MD within the surface casing section to address anticollision concerns. This change drove revisions to measured depths for casing points and total depth. Regulatory stipulations explicitly condition the approval on not deviating above 2065' MD.
Permit Cycle Signals (4)
PROPOSED WORK section of permit modification document (likely Page 9)
2026-03-19 (Exact confidence)
Directly explains the permit modification by stating the operational change that justifies the new approval.
WELLBORE INFORMATION, APPROVED DIRECTIONAL POINTS, and TUBULAR DETAILS sections across permit modification pages
2026-03-19 (Exact confidence)
Specific technical changes to the well plan that are conditioned by the permit approval.
Directional Plan notes and well path diagrams
Relative (Inferred confidence)
Provides a direct technical rationale (anticollision) for the modified directional plan and earlier kick-off, which is core to the permit modification.
Permit Review Policy section (Page 2 or 3)
2026-03-19 (Exact confidence)
A direct regulatory constraint tied to the approved geometry change, ensuring the surface hole deviation stays below a specified depth.
Historical Context (4)
Location within Watford City's Extra-Territorial Jurisdiction and on the Tobacco Garden aquifer triggers persistent site-specific stipulations: closed mud system, no drilling pit, impermeable liner, H2S plan, fencing, berming, casing in rat/mouse holes, spill contingency plan, and required onsite inspection.
Conditions of Approval / Permit Review Policy sections in both original permit and modification · 2025-10-22
These are location-based regulatory constraints that apply to all phases of work on this pad, affecting future drilling, completion, and production operations.
Requirement for deep-set surface casing (13-3/8") that must not penetrate the Mowry Formation, with associated mandates for mud logger, specific cement evaluation (CBL), and a capable rig (no surface casing rigs).
Permit Review Policy sections · 2025-10-22
Imposes ongoing, non-standard well construction requirements for any drilling from this pad due to local geology and regulatory design.
Spacing unit condition (Order 34449) requiring the wellbore to be within the 500' drilling corridor and no closer than 150' setback from north/south boundaries of the 2560-acre unit (Sections 1, 2, 11, 12, T150N, R99W).
NDIC Field Order Info / Conditions of Approval · Unknown
A lasting geometric and legal constraint on well placement and trajectory for this specific spacing unit.
Operator's Best Management Practices (BMP) commitment letter detailing aquifer protection measures, stormwater management, spill response, and site security plans for the Wehrung West pad expansion.
Correspondence (July 22-23, 2025 letter from Yani Durden) · 2025-07-22
Establishes operator-specific operational commitments for the entire pad development, influencing future environmental and safety management.
Operator Pattern
Proactive pre-permit engagement and justification for pad siting in sensitive areas, coupled with requests for waivers on routine requirements.
Submitted detailed analysis of alternative pad locations (June 26, 2025), communicated with city planning (July 17, 2025), and provided a BMP commitment letter (July 22, 2025). Also requested waivers for filter sock container, tubing/packer, and open hole logs prior to the permit modification.
Confidence: High
The permit modification document (dated 2026-03-19) contains explicit, contemporaneous explanations for the approved changes in the 'PROPOSED WORK' and technical data sections. Supporting directional plans and anticollision justifications are integrated. Clear separation exists between the modification-specific signals and historical pad-wide constraints.