OTHER
Wellfile updated - +1 pages
TUFTO 6-7-18-19F 1H
DEVON ENERGY WILLISTON, L.L.C · Williams County, ND · File #42697 · Generated 2026-11-27 02:13
- API
- 3310506795
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The permit contains direct stipulations that condition approval on specific setbacks (including a technical justification for the south setback) and a requirement to drill in conjunction with another well meeting a 1220' setback. A supporting directional plan provides the technical basis for the early kick-off point.
Permit Cycle Signals (4)
Permit Stipulations, Pages 2-3
2026-04-30 (Exact confidence)
Direct regulatory condition anchoring the permit approval; explains the specific setback configuration required for this well.
Permit Stipulations, Page 3
2026-04-30 (Exact confidence)
Direct condition of approval that constrains the drilling sequence and ties this permit's validity to another specific well geometry.
Permit Stipulations, Page 2
2026-04-30 (Exact confidence)
Explains the technical justification for a specific setback waiver (south) that differentiates this permit from routine requirements.
Directional Plan, Page following casing program details
2026-04-24 (Exact confidence)
Supporting technical submission justifying the early kick-off and specific DLS, which is tied to anticollision concerns and likely referenced in permit conditions.
Historical Context (3)
Aquifer stipulation: Requires onsite inspection, closed mud system with no drilling pit, and impermeable liner on the entire location due to well being located on an aquifer.
Permit Stipulations, Pages 2-3 · 2026-04-30
Imposes persistent operational constraints for all phases of location construction and drilling, affecting future execution and requiring Field Inspector coordination.
Deep surface casing requirements: Surface hole/casing must not penetrate the Mowry Formation; mud logger required; no intentional deviation in the 17-1/2-inch surface hole; CBL required on 13-3/8-inch surface casing.
Permit Stipulations, Page 3 · 2026-04-30
These are well-specific construction mandates that persist through drilling operations and must be verified before proceeding, affecting operational planning and sequencing.
Stipulation: 'Devon must set surface casing with a rig capable to account for all contingencies which may be encountered while drilling or running casing (surface casing rigs are not allowed).'
Permit Stipulations, Page 3 · 2026-04-30
Dictates rig capability requirements for the surface casing operation, a forward constraint on equipment selection and operational execution.
Operator Pattern
Operator consistently seeks waivers for routine requirements (filter sock container, tubing/packer, open hole logs) and uses phased drilling (suspension of drilling request).
Sundry notices show approved waivers for filter sock container (drilling phase), tubing/packer, and open hole logs. A suspension of drilling request outlines a plan to drill surface hole with a small rig and return with a larger rig within 90 days.
Confidence: High
The permit document contains explicit, dated stipulations that directly condition the approval. The directional plan is a contemporaneous technical submission that supports permit conditions. Historical waivers and requests are clearly documented and dated.