COMPLETION
Completion: The permit approval is directly conditioned on specific setback requirements justified by well geometry and cementing plans, with additional pre-construction notification requirements.
Updated 2026-08-12 · was Jun 10, 2026 · +65 pages · Full diff →

STATE WOLF FEDERAL 5102 43-33 2B

Whiting Oil & Gas Corporation · McKenzie County, ND · File #42815 · Generated 2026-10-14 06:31

API
3305310770
Target Formation
Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit approval is directly conditioned on specific setback requirements justified by well geometry and cementing plans, with additional pre-construction notification requirements.

Permit Cycle Signals (3)

Approval conditioned on 150' setback from north & south boundaries and 500' setback from east & west boundaries within the 2560-acre spacing unit
Direct
Permit Stipulations
2026-04-07 (Exact confidence)
Specific setback requirements tied to well geometry and spacing unit
South setback based on production liner cemented in the lateral with a wet shoe and ability to frac out the shoe
Direct
Permit Stipulations
2026-04-07 (Exact confidence)
Technical justification for modified setback
Operator must contact NDIC Field Inspector prior to location construction
Direct
Permit Stipulations
2026-04-07 (Exact confidence)
Pre-construction regulatory oversight requirement

Historical Context (3)

Surface Use Agreement executed for off-spacing surface location
Affidavit Affirming Surface Use Agreement · 2026-04-01
Obligation persists for all wells drilled from this pad location
Drill-back notification provided to adjacent operator
Affidavit Affirming Drill-Back Notification · 2025-09-25
Establishes communication protocol for future operations near unit boundaries
Anti-collision measures implemented with 1.2 separation safety factor
Anti-collision Report · 2025-07-30
Ongoing requirement for all future drilling in this area

Operator Pattern

Consistent compliance with off-spacing surface location requirements
Documented SUA execution and drill-back notifications
Confidence: High
All key permit conditions are explicitly documented in regulatory filings with clear dates