OTHER
Approval explicitly conditioned on Order 34361 compliance, engineered setbacks for liner configuration, and validated anticollision clearance
Updated 2026-05-26 · was Apr 20, 2026 · +2 pages · Full diff →

🛢️ ROOSEVELT FEDERAL 5003 13-24 5B

Whiting Oil and Gas Corporation · McKenzie County, ND · File #42845 · Generated 2026-05-26 02:39

API
3305310786
Target Formation
Bakken
Permit Explained
Yes

📋 Permit Cycle Assessment

Approval explicitly conditioned on Order 34361 compliance, engineered setbacks for liner configuration, and validated anticollision clearance

🔍 Permit Cycle Signals (3)

Approval pursuant to Commission Order No. 34361 with specific setbacks
Direct
📄 STIPULATIONS section
📅 2026-04-15 (Exact confidence)
Conditional approval tied to spatially sensitive geological constraints
Special south setback exemption due to cemented production liner/wet shoe design
Direct
📄 Conditions of Approval section
📅 2026-04-15 (Exact confidence)
Waiver of standard setbacks enabled by engineered completion design
Anti-collision analysis submitted confirming >1.2 SF separation from offset wells
Supporting
📄 Anticollision Report (09 March, 2026)
📅 2026-03-09 (Exact confidence)
Mandatory technical justification for directional drilling clearance

📖 Historical Context (2)

Federal minerals coordination required for spacing unit Sections 24,25,36-T150N-R103W
📄 BLM notification email (2026-04-13) · 📅 2026-04-13
BLM oversight persists for future operations in unit
Drill-back policy notification waiver granted due to operator controlling adjacent units
📄 Operator notification waiver request (2026-03-24) · 📅 2026-03-24
Establishes precedent for intra-operator unit crossings
Confidence: High
Direct regulatory correspondence and approved technical plans provide conclusive signals