Potter 4595 33-29 6B

OASIS PETROLEUM NORTH AMERICA LLC · Dunn County, ND · File #43372 · Generated 2026-11-27 02:13

API
3302505249
Target Formation
Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit approval is directly conditioned on specific, non-routine requirements: 1) setback geometry tied to a 'wet shoe' wellbore configuration, 2) site-specific environmental controls (closed mud system, impermeable liner) due to aquifer location, and 3) mandatory pre-construction field inspection. These constraints are explicitly stated in the permit document and justify the permit action.

Permit Cycle Signals (4)

The permit is granted on condition that all portions of the wellbore not isolated by cement be no closer than a 150' setback from the north & south boundaries and 500' setback from the east & west boundaries within the 1920-acre spacing unit. The north setback is based on a production liner cemented in the lateral with a wet shoe and the ability to frac out the shoe.
Direct
Page 1, NDIC Field Order Info
Relative (Inferred confidence)
Directly conditions permit approval with a specific geometry constraint tied to a 'wet shoe' wellbore construction.
Due to the fact this well is located on an aquifer, an onsite inspection is required. Contact the NDIC Field Inspector for site specific stipulations to include but not limited to: Closed Mud System with no drilling pit, and impermeable liner is required on the entire location. Additional site-specific stipulations may be added at the discretion of the Field Inspector.
Direct
Page 1, STIPULATIONS - SPECIAL ATTENTION
Relative (Inferred confidence)
Imposes non-standard, site-specific environmental controls required for permit approval due to aquifer location.
Oasis must contact NDIC Field Inspector Nicole Ewoniuk at 701-290-1527 prior to location construction.
Direct
Page 2, Construction Commencement Notification
Relative (Inferred confidence)
Mandates direct, pre-construction contact with a specific inspector, likely related to the aquifer stipulations.
Based on the azimuth of the proposed lateral, the maximum legal coordinate from the well head at 7" casing point is: 1550' south. Also, based on the azimuth of the proposed lateral the maximum legal coordinates from the well head at Total Depth are: 13983' north and 523' east.
Supporting
Page 3, above OPERATOR INFORMATION
Relative (Inferred confidence)
Provides specific, calculated legal extents for the lateral trajectory, supporting the geometry referenced in the setback conditions.

Historical Context (2)

The wellbore trajectory shows the lateral enters the Bakken Petroleum System outside of the target spacing unit, requiring notification to the adjacent operator per Order No. 31848. Operator requested a waiver as they are the adjacent operator.
End of file, Oasis waiver request letter dated September 2nd, 2026 · 2026-09-02
Confirms a regulatory obligation (notification/waiver) for out-of-unit penetration that was addressed pre-permit but establishes a precedent for similar future operations.
Anti-collision statement details a 1.2 separation safety factor while drilling intermediate sections, increased survey frequency near lateral crossings, and use of gamma ray signatures to identify existing wellbores.
Anti-collision statement within well file content · Unknown
Defines a persistent, operator-specific anti-collision protocol that will govern the drilling execution of this well and others on the pad.

Operator Pattern

Operator (Oasis/Chord Energy) utilizes detailed technical planning packages (trajectory plots, casing design, cement programs) and proactively seeks regulatory waivers (e.g., for adjacent operator notification).
Comprehensive 'TAKTIKAL' directional plan, detailed well diagram with 'wet shoe' configuration, and formal waiver request letter for Order No. 31848 notification.
Confidence: High
The permit document contains explicit, non-standard stipulations and conditions directly tied to the permit approval. Key signals like aquifer requirements and wet shoe-linked setbacks are clearly stated. Supporting technical data is present.