Clark South 33-32-31F XS 1TFH

DEVON ENERGY WILLISTON, L.L.C. · Dunn County, ND · File #43407 · Generated 2026-11-27 02:13

API
3302505257
Target Formation
Three Forks First Bench
Permit Explained
Yes

Permit Cycle Assessment

The permit approval is directly conditioned by regulatory orders and stipulations concerning spacing unit sequencing, specific lateral geometry and setbacks due to casing design, and unstable soils requiring specialized construction protocols and monitoring.

Permit Cycle Signals (5)

Approval conditioned on lateral being approximately down the east-west axis within the 500' drilling corridor and meeting 150' setback from east boundary and 50' setback from west boundary within the 2880-acre spacing unit.
Direct
Page 2 of 11, NDIC Field Order Info
2026-10-14 (Exact confidence)
Sets non-standard, geometry-specific setbacks tied to a fully cemented production liner and inability to frac out the shoe, differentiating from routine horizontal approvals.
Permit includes a 'SPECIAL ATTENTION' stipulation for unstable soils adjacent to the site, requiring cessation of construction if slope is insufficient, notification of NDIC Field Inspector, potential geotechnical report, and a long-term visual monitoring program.
Direct
STIPULATIONS section
Relative (Inferred confidence)
Direct, non-routine regulatory stipulation tied to specific site geology/risk, conditioning permit approval on construction and monitoring protocols.
Order 34200 cited as basis for permit approval, and condition that one horizontal well must be drilled and completed in the 1440-acre laydown spacing unit prior to completing any horizontal well in the 2880-acre laydown lease line spacing unit.
Direct
Page 1 of 11, STIPULATIONS; Page 2 of 11, NDIC Field Order Info
Unknown (Missing confidence)
Regulatory order directly conditions approval on a specific drilling sequence between two defined spacing units, a non-routine operational constraint.
Requirement for operator to contact NDIC Field Inspector Doug Dolyniuk prior to location construction, specified by name and phone number.
Direct
Page 2 of 11, Construction Commencement Notification
Relative (Inferred confidence)
Specific, named inspector contact is a direct pre-construction condition of the permit approval, exceeding generic notification requirements.
January 28, 2024 Geotechnical Report by WHS concludes proposed pad and access road alignment avoids active and non-active landslide deposits, providing design recommendations and supporting pad location.
Supporting
Geotechnical report letter dated January 28th, 2024
2024-01-28 (Exact confidence)
Technical submission addressing the site-specific unstable soils risk identified in the permit stipulations, justifying the proposed construction plan.

Historical Context (4)

Geotechnical report identifies need to avoid landslide deposits for pad/road alignment and provides specific design and construction protocols (benching, over-excavation, compaction, inspection) for stability.
Geotechnical report letter dated January 28th, 2024 · 2024-01-28
Establishes forward-looking engineering constraints for pad construction, drainage control, and long-term slope monitoring that persist beyond permit approval.
Multiple wells drilled from the Clark South Pad target different spacing units, requiring coordination of drilling and completion sequencing as per Order 34200.
STIPULATIONS section (Page 1); Multi-well plats and exhibits · Relative
Creates an operational interdependency between this well and other wells on the pad, dictating the order of operations for the entire pad development.
Surface use agreement affidavit (March 11, 2025) confirms agreement with landowner for multi-well pad drilling off-spacing from surface location in Section 34.
AFFIDAVIT OF SURFACE DAMAGE AGREEMENT · 2025-03-11
Legal agreement governing surface use for the entire pad, establishing landowner relations and surface obligations that persist for all pad operations.
Extensive Right-of-Way (ROW) surveys and legal descriptions (dated Dec 18, 2024) for pad, road, pipeline, utility, and fiber optic access on tribal lands.
ROWS sheets and legal descriptions · 2024-12-18
Defines permanent and temporary land access rights, corridors, and acreage that govern all future infrastructure construction, maintenance, and reclamation for the pad.

Operator Pattern

Operator demonstrates pattern of proactive technical and regulatory engagement for complex pad developments, including geotechnical assessment for slope stability, detailed ROW acquisition, and addressing multi-well spacing unit sequencing.
Geotechnical report pre-dates permit; comprehensive ROW surveys; affidavit for surface agreement; waiver request letter addressing backbuild order requirements for adjacent unit notification.
Confidence: High
Key permit conditions (stipulations, field order, construction contact) are explicitly stated in the permit document. Supporting technical (geotechnical report) and regulatory (waiver letter) submissions are present and clearly linked to permit conditions. Historical documents are well-dated and establish clear forward obligations.