OTHER
Wellfile updated - +1 pages
First detected 2026-10-28 · was Oct 22, 2026 · +1 page · Full diff →

BULLDOG FED 35-26-23 1HF

Phoenix Operating LLC · McKenzie County, ND · File #43421 · Generated 2026-11-27 02:13

API
3305310907
Target Formation
Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit approval is directly conditioned by Order 35181 with specific setbacks, a waiver for lateral exit notification, a federal minerals coordination requirement, and a mandate to drill with an offset well meeting a 1220' setback.

Permit Cycle Signals (4)

Order 35181 grants permit approval conditional on specific setbacks (150' N/S, 500' E/W) within the 1920-acre spacing unit, with north setback based on cemented production liner with wet shoe.
Direct
Stipulations section
Relative (Inferred confidence)
This is the direct regulatory order anchoring the permit approval, specifying non-standard setbacks tied to well geometry and cementing plan.
Waiver request for backbuild notification (Order 31848) due to lateral exiting spacing unit, citing no current operator in adjacent unit.
Supporting
Letter dated April 7th, 2026
2026-04-07 (Exact confidence)
Justifies non-compliance with standard notification requirement for laterals crossing unit boundaries, a prerequisite for permit.
Engineer email requiring operator contact BLM due to federal minerals in spacing unit (Sections 23, 26, 35, T145N, R98W).
Direct
Email from Nathaniel Erbele dated 10/19/2026
2026-10-19 (Exact confidence)
Direct pre-approval condition from regulator requiring federal coordination, directly tied to permit approval date.
Requirement to drill in conjunction with a well meeting 1220' setback from east/west boundaries to justify spacing unit.
Direct
Page 2 of permit
Unknown (Missing confidence)
Specific, non-routine condition linking this permit's approval to the drilling of another well with a precise geometric constraint.

Historical Context (2)

Stipulation requiring wellbore portions not isolated by cement maintain 150'/500' setbacks within the 1920-acre unit.
Stipulations section · Relative
This cementing and geometric constraint is a persistent operational requirement for the entire well life, affecting future workovers or re-entries.
Waiver for standard notification when lateral exits spacing unit (per Order 31848) remains in effect for these wellbores.
Letter dated April 7th, 2026 · 2026-04-07
This waiver covers the drilling and completion of these specific laterals; any future operations impacting adjacent units may reference this precedent.

Operator Pattern

Proactive regulatory engagement: seeks waivers (backbuild notification), submits detailed directional plans, and coordinates with federal agencies as directed.
Submitted waiver request letter for lateral exit; included detailed directional survey and well plan; BLM coordination was initiated per regulator email.
Confidence: High
Document contains explicit regulatory orders, waiver request, and direct engineer communications that clearly condition the permit approval dated 10/19/2026. Key dates and requirements are explicitly stated.