GARFIELD FEDERAL 5003 43-15 3B
Whiting Oil and Gas Corporation · McKenzie County, ND · File #43433 · Generated 2026-11-27 02:13
- API
- 3305310914
- Target Formation
- Middle Creek-Bakken Pool
- Permit Explained
- Yes
Permit Cycle Assessment
The permit approval is directly explained by contemporaneous stipulations and correspondence. The permit is conditioned on non-routine setbacks tied to a wet shoe design and a requirement to drill back-to-back with another well. Pre-approval correspondence confirms BLM coordination and a waiver for adjacent operator notification.
Permit Cycle Signals (4)
Permit Information - Stipulations / Conditions of Approval
2026-10-23 (Exact confidence)
Permit is explicitly anchored to Commission Order No. 31756 and includes non-routine setback justification tied to a specific wellbore construction (wet shoe).
Permit Information - Stipulations (SPECIAL ATTENTION)
2026-10-23 (Exact confidence)
Directly conditions permit approval on a specific, non-standard drilling sequence and geometry relative to another well.
Email from Emma V. Neigum dated 2026-10-22
2026-10-22 (Exact confidence)
Regulatory pre-condition for permit approval on federal lands. Sent one day before permit approval date.
Letter from Melissa Szudera dated 2026-10-06
2026-10-06 (Exact confidence)
Directly addresses a regulatory pre-condition (drill-back policy) for a permit where the wellbore enters an adjacent unit, justifying waiver.
Historical Context (2)
Wet shoe wellbore design (intentionally uncemented annulus at liner toe) detailed in operator's drilling plan.
Operator Drill Statements - Wet Shoe configuration discussion · Unknown
Specifics of the cemented liner and uncemented annulus affect completion operations (toe initiation) and are a premise for the north setback condition in the permit.
Facility design uses an indirect heater with a setback exemption (NDIC Case No. 28949 Order No. 31500).
Operator Drill Statements - Facility Statement · Unknown
Establishes a permanent, approved variance from standard facility setback rules for this location, impacting future pad layout and operations.
Operator Pattern
Systematic pre-permit submission of drill-back policy waivers and federal mineral coordination.
Waiver request letter for adjacent operator notification (Oct 6) and prompt response to BLM notification requirement (Oct 22) demonstrate a pattern of addressing regulatory pre-conditions ahead of permit approval.
Confidence: High
Core permit conditions and pre-approval correspondence are explicitly documented in the file. Dates are clear and logically precede the permit approval. No critical information appears missing.