STRANDED CAT 28-21-16-9 2H
DEVON ENERGY WILLISTON, L.L.C. · Williams County, ND · File #43441 · Generated 2026-11-27 02:13
- API
- 3310506925
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The permit approval is directly explained by Commission Order No. 36219, which conditions approval on specific setbacks. The north/south setback is explicitly tied to the non-routine completion design featuring a cemented production liner with a wet shoe.
Permit Cycle Signals (3)
Permit Information, Stipulations section
2026-10-29 (Exact confidence)
Direct regulatory order conditioning permit approval on specific geometry (150' N/S setback) justified by a technical completion design (cemented liner with wet shoe).
Operator Assertions section
Relative (Inferred confidence)
Required submission supporting permit approval by demonstrating anti-collision review for nearby wells.
Proposed Drilling Plan, Section Details
2026-08-31 (Exact confidence)
Technical justification submitted pre-permit for the completion method that conditions the permit's north/south setback approval.
Historical Context (1)
Devon's September 2, 2026 letter references NDIC Orders 31973 and 31848, requiring notification and information sharing when drilling into adjacent spacing units.
Operator letter dated September 2nd, 2026 · 2026-09-02
These orders impose a persistent regulatory obligation for future wells that traverse adjacent units, requiring plan disclosure and notification.
Confidence: High
Key permit conditioning language (Order 36219 and setback justification) is clearly stated in the permit stipulations. Supporting technical design is documented in the drilling plan and survey report. Historical regulatory orders are explicitly referenced in a dated operator letter.