KODA RESOURCES OPERATING, LLC · Divide County, ND · File #43448 · Generated 2026-11-27 02:13

API
3302301917
Target Formation
Middle Bakken
Permit Explained
Yes

Permit Cycle Assessment

Permit approval is directly justified by Commission Order 35874 (setbacks), aquifer-based stipulations requiring inspection, directional coordinate constraints, and a waiver request for off-spacing notification.

Permit Cycle Signals (4)

Permit approval is granted pursuant to Commission Order No. 35874, conditioned on wellbore setbacks (150' north/south, 500' east/west) within the 2880-acre spacing unit. The south setback is based on a production liner cemented in the lateral with a wet shoe and ability to frac out the shoe.
Direct
Page 1, STIPULATIONS section
Unknown (Missing confidence)
Direct regulatory order (35874) conditions approval on specific geometry and completion design, differentiating from routine setbacks.
Regulatory stipulation: due to location on an aquifer, onsite inspection is required with site-specific stipulations including closed mud system with no drilling pit and impermeable liner on entire location. Additional stipulations may be added by Field Inspector.
Direct
Page 1, SPECIAL ATTENTION stipulation
2026-11-03 (Exact confidence)
Direct regulatory condition tied to specific geologic hazard (aquifer) requiring inspection and non-standard containment.
Based on azimuth of proposed lateral, legal coordinate requirements: minimum 906' south at 7" casing point, maximum 16494' south at Total Depth.
Direct
Page 2, Conditions of Approval
2026-11-03 (Exact confidence)
Specific directional constraints justifying permit approval for this lateral geometry, not boilerplate.
Operator requests waiver from NDIC Order 31973 notification requirements because KODA is the operator of the adjacent spacing unit the wellbore traverses.
Supporting
Letter from KODA to NDIC dated September 21, 2026
2026-09-21 (Exact confidence)
Supporting waiver request that addresses regulatory condition for off-spacing entry, directly tied to permit approval.

Historical Context (3)

NDIC Order 31973 (referenced in waiver request) imposes notification requirements on operators when a wellbore enters an adjacent spacing unit from outside the target unit.
KODA waiver request letter dated September 21, 2026 · Unknown
This order establishes a persistent regulatory obligation for any future wells with similar geometry entering adjacent units, requiring either notification or justification for waiver.
Surface Use Agreement executed October 14, 2025, covering all wells on the Ale 15 pad, including ALE 1534-6BH.
Affidavit of Surface Use Agreement · 2025-10-14
Creates a binding surface owner obligation that persists for all operations on this pad, affecting future drilling, completion, and production activities.
Aquifer location triggers ongoing operational constraints: closed mud system, impermeable liner, and potential for additional site-specific stipulations from Field Inspector.
Page 1, SPECIAL ATTENTION stipulation · 2026-11-03
Geologic hazard imposes persistent design and inspection requirements for all pad operations, not just this permit cycle.

Operator Pattern

KODA utilizes multi-well pads with complex trajectories entering spacing units from outside, requiring regulatory coordination (waivers for Order 31973).
Waiver request for four wells (ALE 1534-5BH, -6BH, -7BH, ALE 1535-8BH) referencing Order 31973; pad layout shows eight wells with shared surface location.
Confidence: High
Permit contains explicit regulatory orders (35874, aquifer stipulations), directional constraints, and a contemporaneous waiver request directly tied to approval. Historical signals are clearly separated and relevant.