OTHER
Wellfile updated - +1 pages
ALE 1534-2BHN
KODA Resources Operating, LLC · Divide County, ND · File #43452 · Generated 2026-11-27 02:13
- API
- 3302301921
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The file contains contemporaneous permit-cycle documentation. The 11/04/2026 approval is conditioned on Commission Order No. 35873, an aquifer-based field-inspection requirement, and explicit lateral coordinate limits. These items directly explain or condition the anchored permit approval.
Permit Cycle Signals (3)
NDIC permit information, Page 1, STIPULATIONS - NDIC Field Order Info
2026-11-04 (Exact confidence)
The setback is not generic; it is linked to the completion design and wet shoe/frac-out toe, making it a permit-specific geometry condition.
NDIC permit information, Page 1, STIPULATIONS - SPECIAL ATTENTION
2026-11-04 (Exact confidence)
The approval expressly ties field inspection and containment conditions to an aquifer concern, even though the operator assertion elsewhere says the pad is not on an aquifer.
NDIC permit information, Page 2, Conditions of Approval
2026-11-04 (Exact confidence)
The permit defines exact directional-coordinate limits tied to the planned lateral path and spacing-unit legality, rather than routine APD language.
Historical Context (3)
KODA submitted a letter requesting a waiver from NDIC Order No. 31973, which would require providing directional drilling and completion plan details, drilling start date, and contact information to the operator of an adjacent spacing unit; the permit file does not show that the waiver was granted.
Attachment, letter to Todd Holweger regarding NDIC Order No. 31973, undated · Unknown
If the waiver is not granted, the adjacent-spacing-unit disclosure obligation persists and could require communication or production of plan details outside this permit approval.
An executed Surface Use Agreement effective 10/14/2025 covers the Ale 15 replacement pad wells, including ALE 1534-2BHN, and addresses injuries and damages to the surface owner as a result of drilling, completion, and production operations.
Attachment, Affidavit of Surface Use Agreement executed 09/21/2026 · 2025-10-14
Private surface access, liability, and damage-resolution obligations persist for the pad beyond the permit and can affect site construction, operations, and remediation commitments.
The KLX Directional Planning / Anti-Collision Report dated 06 August 2026 documents the planned path, target points, casing points, and avoidance analysis for the ALE 1534-2BHN wellbore relative to pad and offset wells.
Attachment, KLX Directional Planning / Anti-Collision Report · 2026-08-06
Execution must remain aligned with the planned path, spacing limits, and collision-avoidance assumptions; later changes or actual surveys that deviate from this analysis can trigger additional coordination or approval needs.
Confidence: High
The permit approval date, API, file number, and direct regulatory conditions are explicit. Some ancillary materials are undated, but they are treated as historical context rather than permit-cycle signals.