Cottonwood 102-3421H
EOG Resources, Inc. · Mountrail County, ND · File #43470 · Generated 2026-11-27 02:13
- API
- 3306105728
- Target Formation
- Three Forks First Bench
- Permit Explained
- Yes
Permit Cycle Assessment
The anchored approval is explained by contemporaneous permit-cycle documentation. The permit was issued pursuant to Commission Orders 35122 and 35123, with explicit setbacks, a liner wet-shoe condition, a maximum legal coordinate, and a unit formation definition that collectively justify the specific approval.
Permit Cycle Signals (4)
NDIC Permit Information, Page 1, NDIC Field Order Info
2026-11-10 (Exact confidence)
This is the explicit regulatory basis for the anchored permit action and directly sets the allowable well-bore geometry in the unit.
NDIC Permit Information, Page 1, Conditions of Approval
2026-11-10 (Exact confidence)
This non-routine completion condition justifies the permitted near-boundary geometry and differentiates the approval from routine horizontal well approvals.
NDIC Permit Information, Page 2, Conditions of Approval
2026-11-10 (Exact confidence)
This imposes a well-specific directional constraint that is required for compliance with the approved unit boundaries.
NDIC Permit Information, Page 1, Conditions of Approval
2026-11-10 (Inferred confidence)
The unit formation definition is part of the regulatory framework used to condition the approval, but the order date is not expressly shown in the permit text.
Historical Context (3)
A NDIC engineering technician emailed EOG on 11/5/2026 stating that the permit application appears to be within a spacing unit that may be subject to a Federal permit and directed contact with BLM to ensure proper documentation.
Outlook email from Doug Jackson, NDIC, 11/5/2026 · 2026-11-05
The federal-minerals/BLM documentation issue is not stated as a resolved permit condition in the approved permit text and could affect future construction, completion, production, or regulatory compliance.
The operator must give prior written notice, up to thirty-one days and not less than twenty-one days, to any operator of a well completed in the same or adjacent pool when completion intervals are within 2,640 feet of one another, including emergency contact and planned dates.
NDIC Permit Information, Page 7, Operator Assertions · 2026-11-10
This obligation persists beyond permit issuance and directly constrains future hydraulic fracturing scheduling on adjacent wells.
The Mission Canyon Formation is identified as a known H2S zone in the basin, and the APD states pressure control equipment and an H2S plan are required for the operation.
EOG Cottonwood 102-3421H APD Drilling Plan, Sections 1 and 6 · Unknown
The H2S/pressure-control exposure is a forward operational constraint during drilling and completion, though the attached H2S plan is not present in the extracted file.
Operator Pattern
EOG is developing a multi-well pad in the Ross 5 NWNW/CTB/NENW area under the Alger-Bakken Unit, using long horizontal Three Forks wells with directional targets constrained by unit boundaries and production-liner/wet-shoe completion assumptions.
Permit plat and pad layout identify the ROSS 5 NWNW pad and multiple Cottonwood wells; permit stipulations reference Alger-Bakken Unit orders, setbacks, liner wet shoe, and maximum legal coordinate.
Confidence: High
The permit information is dated to the approval date 11/10/2026 and contains explicit commission-order-based stipulations that condition the anchored approval.