Cottonwood 20-3422H

EOG Resources, Inc. · Mountrail County, ND · File #43475 · Generated 2026-11-27 02:13

API
3306105733
Target Formation
Middle Bakken
Permit Explained
Yes

Permit Cycle Assessment

The permit file contains contemporaneous documentation that explains and conditions the November 10, 2026 approval. NDIC expressly ties the approval to Commission Orders 35122 and 35123, Alger-Bakken Unit setbacks, a wet-shoe production-liner completion condition, and a total-depth coordinate limit. The filed directional plan, hydraulic-fracture-fluid affidavit, and BLM federal-permit email are contemporaneous permit-cycle materials that support the geometry, completion constraints, and federal-minerals screening associated with the approval.

Permit Cycle Signals (5)

NDIC approval is conditioned on Commission Order No. 35122 and 35123, requiring portions of the well bore not isolated by cement to remain no closer than the 150-foot setback from the north and south Alger-Bakken Unit boundaries and the 500-foot setback from the east and west boundaries, and stating that the north setback is based on a production liner cemented in the lateral with a wet shoe and the ability to frac out the shoe.
Direct
Permit Information - STIPULATIONS; NDIC Field Order Info and Conditions of Approval, page 1
2026-11-10 (Exact confidence)
This stipulation is the regulator's direct condition for approving the horizontal well path and unit compliance.
The permit states that the rectangular coordinate system is used to verify well-bore legality and, based on the proposed lateral azimuth, sets a maximum legal coordinate from the well head at total depth of 16,472 feet north.
Direct
Permit Information - STIPULATIONS and Conditions of Approval, pages 1-2
2026-11-10 (Exact confidence)
This converts the horizontal geometry into a binding legal coordinate limit specific to this well.
EOG's directional planning report for the APD plan establishes the proposed KOP at 9,847 feet MD, TD at 25,172 feet MD, azimuth of 357 degrees, and bottom-hole coordinates that support the permit's coordinate and setback analysis.
Supporting
WELL INFORMATION - APPROVED DIRECTIONAL POINTS; EOG APD directional planning report and COMPASS planning pages
2026-08-06 (Exact confidence)
The technical plan shows the specific geometry the regulator evaluated before imposing the coordinate and setback conditions.
A notarized operator affidavit for the subject wells states that EOG does not use diesel fuel, as defined by EPA, in fluids used for underground hydraulic fracturing.
Supporting
AFFIDAVIT IN RE HYDRAULIC FRACTURE FLUIDS; acknowledgement dated September 28, 2026
2026-09-28 (Exact confidence)
The affidavit supports the NDIC diesel-fracture condition referenced in the approval assertions and removes a completion-related approval obstacle.
NDIC permitting emailed EOG five days before approval that the permit application may be within a spacing unit subject to a federal permit and directed EOG to contact BLM to ensure federal documentation was filed.
Direct
NDIC email from Doug Jackson to Jennifer Yu dated 11/05/2026
2026-11-05 (Exact confidence)
It is a contemporaneous regulator condition tied to federal minerals in the Alger-Bakken Unit and appears in the permit-approval cycle immediately before approval.

Historical Context (3)

The Alger-Bakken Unit formation is defined by Order No. 35122 as the interval from 50 feet above the top of the Bakken Formation to above the top of the Birdbear Formation, identified in the Erie #44-19H reference well at depths 9,894 to 10,310 feet from KB 2,460.
Permit Information - Conditions of Approval, page 1 · Unknown
Future targeting, cement isolation, completion, and unit-boundary compliance must be evaluated against this unitized interval definition rather than a simple Bakken marker.
The operator affirms that any shortening of casing point, lengthening at total depth, or change in completion technique within the Bakken-Three Forks Petroleum System must have prior NDIC approval.
Operator assertions and approved permit conditions, page 9 · 2026-09-29
This creates a continuing regulatory gate over drilling depth and completion changes during execution of the permit.
The APD geologic plan identifies the Base Last Salt and Mission Canyon interval as an anticipated H2S zone and references an attached H2S plan.
APD drilling plan, anticipated geologic markers and abnormal conditions pages · Unknown
H2S control, well control, safety equipment, and personnel protections must be maintained during drilling and later operations at depth.

Operator Pattern

EOG Resources is pursuing unitized multi-well horizontal development from the Ross 5 NWNW pad under the Alger-Bakken Unit, using long laterals, wet-shoe production liners, and standard Bakken-Three Forks regulatory controls.
Permit stipulations reference Orders 35122 and 35123 and unit setbacks; the pad plat and APD plan include Cottonwood 102, 15, 103, 17, 108, and 20 wells; the directional plan shows a 25,172-foot MD lateral; the application asserts NDIC prior approval for casing/TD/completion changes.
Confidence: High
The permit approval date, API, file number, operator, county, target, unit orders, and primary stipulations are explicit. Some plat and geologic dates are present, and OCR imperfections do not prevent identification of contemporaneous permit-cycle documentation.