Potter 4595 33-29 7BX

Oasis Petroleum North America LLC · Dunn County, ND · File #43481 · Generated 2026-11-27 02:13

API
3302505262
Target Formation
Middle Bakken
Permit Explained
Yes

Permit Cycle Assessment

The well file contains contemporaneous permit-cycle documentation explaining the 11/12/2026 approval. The permit itself invokes Commission Order No. 35946, sets a wet-shoecorridor and north/south setback condition, and adds an aquifer special-attention inspection condition. Pre-permit September 2026 documents support those conditions by identifying off-spacing traversal and describing the wet-shoe completion method.

Permit Cycle Signals (4)

Commission Order No. 35946 approval is conditioned on keeping portions of the bore not isolated by cement along the north-south axis within a 500-foot drilling corridor and no closer than 150-foot setbacks on the north and south boundaries, expressly tied to a production liner cemented in the lateral with a wet shoe.
Direct
Permit Information page 2, NDIC Field Order Info
2026-11-12 (Exact confidence)
This condition directly limits the approved wellbore geometry and completion method, making it a permit-specific justification rather than routine APD language.
NDIC special attention condition requires an onsite inspection and site-specific stipulations because the well is located on an aquifer.
Direct
Permit Information page 2, SPECIAL ATTENTION
2026-11-12 (Exact confidence)
The aquifer concern is an express condition tied to approval, elevating otherwise routine closed-mud/liner requirements to a non-routine site-specific condition.
The Chord Energy/Oasis submission identifies the proposed wellbore entering the Bakken outside the target spacing unit and requests waiver of adjacent-operator notification because Oasis operates the adjacent spacing unit.
Supporting
Chord Energy letter to NDIC dated September 2, 2026, RE: Potter 4595 33-29 #2BX, #3B, #4B, #5B, #6B, and #7BX
2026-09-02 (Exact confidence)
This pre-permit material addresses the off-spacing traversal and adjacent-unit approval concern relevant to the 11/12/2026 permit action.
The submitted wet-shoe design shows intentional over-displacement of cement near the toe, creating an uncemented annulus to enable first-stage pump-down perforating and explain the permit’s north setback condition.
Supporting
Submitted plan, Section 1.11 Wet Shoe; Taktical plan dated 2026-09-02
2026-09-02 (Inferred confidence)
It provides the technical basis for the wet-shoe setback language in the permit and differentiates this completion geometry from routine horizontal approvals.

Historical Context (0)

No historical signals identified.

Operator Pattern

Operator seeks off-spacing or adjacent-unit notification relief when it is the operator of the adjacent spacing unit and uses lateral completion configurations that create regulatory setback constraints.
September 2, 2026 Chord Energy/Oasis letter requests notification waiver under Order No. 31848 because Oasis operates the adjacent spacing unit; permit stipulations dated November 12, 2026 tie a north setback to a production liner with a wet shoe.
Confidence: High
The permit pages carry an explicit approval date of 11/12/2026, name the operator, well, API, and file number, and state direct conditions tied to Commission Order No. 35946, wet-shoe setback, and aquifer sensitivity. Pre-permit supporting documents dated 09/02/2026 address off-spacing traversal and wet-shoe completion logic.