AMBER 2133-3BH
KODA RESOURCES OPERATING, LLC · Divide County, ND · File #43503 · Generated 2026-11-27 02:13
- API
- 3302301929
- Target Formation
- Middle Bakken
- Permit Explained
- Yes
Permit Cycle Assessment
The permit file contains contemporaneous documentation that explains the 11/19/2026 permit approval. The key explanation is Commission Order No. 35707, which conditions approval on the 1920-acre spacing unit setbacks and expressly ties the south setback to the proposed wet-shoe production liner and frac-out capability. The aquifer stipulation and directional plan also directly justify the permit conditions.
Permit Cycle Signals (3)
Page 1, Permit Information, STIPULATIONS, NDIC Field Order Info
2026-11-19 (Inferred confidence)
This condition directly justifies the permit approval by tying legal setback relief to a non-routine completion geometry rather than ordinary surface placement.
Page 1, Permit Information, STIPULATIONS, SPECIAL ATTENTION
2026-11-19 (Exact confidence)
This is a regulator-issued condition explaining protective constraints for this permit due to a specific aquifer risk.
KLX Directional Drilling Well Planning Report dated 02 November, 2026; Koda Resources Drilling Plan, Sections 3, 5, and Production Casing / Liner
2026-11-02 (Exact confidence)
It supports the wet-shoe and lateral geometry assumptions relied on by NDIC in the Commission Order No. 35707 condition.
Historical Context (4)
Executed Surface Use Agreement effective October 10, 2024 between KODA and the David E Jensen QTIP Trust covers injuries or damages from drilling, completing, and producing wells at the Amber 21 pad.
Affidavit of Surface Use Agreement dated November 3, 2026, near end of file · 2024-10-10
It remains a surface liability and access framework for future pad operations and may govern compensation or disputes during execution.
NDIC guidance effective June 1, 2014 requires a leakproof, covered, placarded on-site container for filters during spud, clean-out, completion, and flowback whenever filtration is used; waiver only via Sundry Notice.
Letter dated July 29, 2026, Mark F. Bohrere/NDIC · 2026-07-29
It imposes ongoing site and waste-handling obligations for this well and similar future wells unless waived.
Operator acknowledgment states that changes, shortening of casing point, lengthening at total depth, or change in completion technique within the Bakken-Three Forks Petroleum System require prior NDIC approval.
Page 10, Conditions of Approval / Operator understandings · 2026-11-19
It constrains future execution and redesign after permit approval; any change in the target well plan requires a prior regulatory step.
Operator acknowledgment requires written notice 21 to 31 days before hydraulic fracturing to adjacent same or adjacent pool operators when completion intervals are within 2,640 feet, with 24-hour emergency contact and scheduling information.
Page 8, Operator Assertions · 2026-11-19
It affects future fracture scheduling and coordination beyond this permit.
Operator Pattern
KODA appears to reoccupy established pads and seek regulatory waivers to develop adjacent spacing units as a coordinated multi-well operator.
November 3, 2026 waiver and affidavit letters reference the Amber 21 pad, three 1920-acre DSUs, high working interests, and requests to waive the three-day waiting period and adjacent operator notification.
Confidence: High
The permit approval date and conditions are explicit, and the directional report and waiver letters are dated. Minor OCR and plat inconsistencies do not affect the identified permit-cycle explanation.