TUFTO 6-7-18-19F 2TFH

DEVON ENERGY WILLISTON, L.L.C · Williams County, ND · File #42698 · Generated 2026-11-27 02:13

API
3310506796
Target Formation
Three Forks First Bench (B1)
Permit Explained
Yes

Permit Cycle Assessment

The approved permit is explicitly conditioned by regulatory stipulations on setbacks tied to Order 34491 and well geometry. Multiple waivers (open-hole logs, filter sock, tubing/packer) approved with specific technical justifications directly explain non-routine elements of the permit.

Permit Cycle Signals (4)

Approval subject to 150' setback from north/south boundaries and 1220' setback from east/west boundaries within the 2560-acre spacing unit per Commission Order No. 34491. The south setback is based on a production liner cemented in the lateral with a wet shoe and ability to frac out the shoe.
Direct
Permit Information / STIPULATIONS
2026-02-06 (Exact confidence)
Specific, non-standard setback tied to well geometry (wet shoe) and cemented liner rather than generic spacing policy. Conditions the well's lateral placement and completion design.
Waiver of open hole logging requirement granted, referencing offset well Folvag 5-8 7H (NDIC #30379) within a mile to establish formation tops. Requires GR-CBL from TD to ground level.
Direct
Open Hole Log Waiver Sundry
2026-02-11 (Exact confidence)
Justifies deviation from standard logging rules, referencing a specific technical justification (offset data) and imposing a compensating control (GR-CBL).
Waiver of filter sock container requirement for drilling phase only, approved on basis that Devon does not use filter media during drilling.
Direct
Filter Sock Container Waiver Sundry
2026-03-03 (Exact confidence)
Modifies a standard permit condition (container on-site at spud) based on operator's specific operational plan.
Tubing/packer variance request approved based on assurances including new high-burst casing, safety factor, and pressure monitoring during flowback.
Direct
Tubing/Packer Waiver Sundry
2026-03-02 (Exact confidence)
Justifies waiver of standard completion requirement with specific engineering assurances.

Historical Context (2)

State Geologist's core and sample collection requirement: cuttings from Base of Last Charles Salt at 30' intervals in vertical/build, 200' in lateral, with shipment deadlines.
Cores and Samples Letter from Ross Edison · 2026-02-09
Imposes a persistent data collection and reporting obligation for the well's drilling operations, independent of the permit approval.
Surface location is off-spacing from target unit (pad in Section 31, wellbore targets unit in Sections 6,7,18,19). Operator provided affidavit of surface damage agreement with landowner.
Affidavit of Surface Damage Agreement · 2025-11-20
Creates a lasting surface use obligation and potential liability with the surface owner for the well's entire lifecycle due to off-pattern drilling.
Confidence: High
Key approval documents (permit with stipulations, approved waiver sundries) are present with exact dates. The permit-cycle explanation is clearly separated from ongoing obligations (core samples, surface agreement). No critical dates are missing.