Approval conditioned by Order 35144 setbacks with technical justification for south setback variance via cemented liner design. Anticollision analysis validates well spacing.
Updated 2026-05-26 ยท was Apr 28, 2026 ยท Full diff โ†’

๐Ÿ›ข๏ธ GO-Daniel-156-98-0322H-3

Hess Bakken Investments II, LLC ยท Williams County, ND ยท File #42860 ยท Generated 2026-05-26 02:39

API
3310506823
Target Formation
Middle Bakken
Permit Explained
Yes

๐Ÿ“‹ Permit Cycle Assessment

Approval conditioned by Order 35144 setbacks with technical justification for south setback variance via cemented liner design. Anticollision analysis validates well spacing.

๐Ÿ” Permit Cycle Signals (3)

Commission Order No. 35144 conditions approval with specific setbacks: 150' from north & south boundaries, 500' from east & west boundaries.
Direct
๐Ÿ“„ Permit Stipulations
๐Ÿ“… 2026-04-24 (Exact confidence)
Sets non-standard geometric constraints for well placement.
South setback allowance based on cemented production liner with wet shoe enabling frac operations.
Direct
๐Ÿ“„ Conditions of Approval
๐Ÿ“… 2026-04-24 (Exact confidence)
Technical justification for reduced setback.
Anticollision report demonstrating >1.5 separation factor against offset wells, including Olson 2-3H and Strahan 15-22H.
Supporting
๐Ÿ“„ Anticollision Report
๐Ÿ“… 2026-03-03 (Exact confidence)
Mitigates collision risk in dense drilling area.

๐Ÿ“– Historical Context (2)

Affidavit confirming Hess waived Order 31848 requirements as operator of adjacent units.
๐Ÿ“„ Letter dated 2026-03-16 ยท ๐Ÿ“… 2026-03-16
Establishes precedent for intra-operator unit crossings.
BLM federal minerals notification requirement for spacing unit Sections 3,10,15,22 T156N-R98W.
๐Ÿ“„ Email from NDIC Permitting ยท ๐Ÿ“… 2026-04-23
Ongoing federal regulatory coordination obligation.
Confidence: High