β Back to Daily Permits
OTHER
Permit approval is directly conditioned on Commission Order 35507 setbacks, field inspection contact, and specified completion techniques.
π’οΈ ALBERT SOUTH 34-33-32 2H
DEVON ENERGY WILLISTON, L.L.C Β· McKenzie County, ND Β· File #42885 Β· Generated 2026-08-28 04:09
- API
- 3305310797
- Target Formation
- Foreman Butte-Bakken Pool
- Permit Explained
- Yes
π Permit Cycle Assessment
Permit approval is directly conditioned on Commission Order 35507 setbacks, field inspection contact, and specified completion techniques.
π Permit Cycle Signals (3)
π Permit Information - Stipulations
π
2026-04-30 (Exact confidence)
Conditions approval with unique geometry constraints
π Permit Information - Stipulations
π
2026-04-30 (Exact confidence)
PreΒ Β Β Β Β Β Permit requirement tied to field verification
π Permit Information - Stipulations
π
2026-04-30 (Exact confidence)
Specifies completion technique conditioning approval
π Historical Context (2)
Surface use agreement covering multiple off-spacing wells from shared pad
π Affidavit of Surface Damage Agreement Β· π
2025-12-15
Defines ongoing land use permissions for multi-well development
Filter sock container requirement persisting through completion phases
π NDIC Regulatory Letter Β· π
2014-06-01
Imposes continuous waste management obligations during operations
Confidence: High
Explicit regulatory references and dated operational requirements found in primary documents