← Back to Daily Permits
OTHER
Permit approval is directly conditioned on Commission Order 35507 setbacks, field inspection contact, and specified completion techniques.
Updated 2026-08-28 Β· was Jun 8, 2026 Β· Full diff β†’

πŸ›’οΈ ALBERT SOUTH 34-33-32 2H

DEVON ENERGY WILLISTON, L.L.C Β· McKenzie County, ND Β· File #42885 Β· Generated 2026-08-28 04:09

API
3305310797
Target Formation
Foreman Butte-Bakken Pool
Permit Explained
Yes

πŸ“‹ Permit Cycle Assessment

Permit approval is directly conditioned on Commission Order 35507 setbacks, field inspection contact, and specified completion techniques.

πŸ” Permit Cycle Signals (3)

Approval to drill granted under Commission Order No. 35507, with specific setback conditions
Direct
πŸ“„ Permit Information - Stipulations
πŸ“… 2026-04-30 (Exact confidence)
Conditions approval with unique geometry constraints
Requirement to contact NDIC Field Inspector prior to location construction
Direct
πŸ“„ Permit Information - Stipulations
πŸ“… 2026-04-30 (Exact confidence)
PreΒ Β Β Β Β Β Permit requirement tied to field verification
Production liner cemented in lateral with wet shoe for frac out capability
Direct
πŸ“„ Permit Information - Stipulations
πŸ“… 2026-04-30 (Exact confidence)
Specifies completion technique conditioning approval

πŸ“– Historical Context (2)

Surface use agreement covering multiple off-spacing wells from shared pad
πŸ“„ Affidavit of Surface Damage Agreement Β· πŸ“… 2025-12-15
Defines ongoing land use permissions for multi-well development
Filter sock container requirement persisting through completion phases
πŸ“„ NDIC Regulatory Letter Β· πŸ“… 2014-06-01
Imposes continuous waste management obligations during operations
Confidence: High
Explicit regulatory references and dated operational requirements found in primary documents